IA150 Incremental Load - SSAS

Sort:
You are not authorized to post a reply.
Author
Messages
Scott H
New Member
Posts: 1
New Member

    Hi -

    Not sure this is the correct subforum, but I was wondering if someone could help with a question regarding the options in running and incremental data load in IA150.

    The options are:

    Build Cube: Y/N

    Process Cube: Y/N

    Fact Table Options: C/I/N (obviously I here)

    Create All Dimensions: Y/N

    We've run a complete load with all setting set to Y. We ran an incremental load after entering some changes in Lawson with all options set to Y and Fact Table set to I (Incremental). Problem is alot of the data was wiped out after running that job. What should the options be set to when running an incremental job???

    Thanks for any input!

    Scott