How to link REQ # to PO# in Lawson Tables
 1 Replies
 0 Subscribed to this topic
 45 Subscribed to this forum
Sort:
You are not authorized to post a reply.
Author Messages
Laurie DeSantis
Supply Chain Application Systems Analyst
Private
New Member
(3 points)
New Member
Posts:3


Send Message:

--
4/6/2023 7:17 PM

    We have a report to run for a specific company and cost center.  The report needs to contain REQ# and PO#.  Which table(s) will obtain this information? Is there a current PO table that contains REQ# ?  We've tried REQLINE AND PORECLINE along with REQHEADER but are unable to link to get a PO#.  

     

    Joe Carfagno
    IT Supervisor - ERP
    Private
    New Member
    (7 points)
    New Member
    Posts:5


    Send Message:

    --
    4/11/2023 12:55 PM
    Hi Laurie,
    Please look at POLINESRC. The Origin_CD should be 'RQ'. The Source_Doc_N field contains the Requisition Number. The Requester field has the requester ID.