Kyle Jorgensen
Veteran Member Send Private Message
Posts: 122
Veteran Member

Is anyone using Control-M (a cross-application and cross-platform workload management tool) with Lawson and/or Landmark?

If not Control-M, any other workload management tool?

Thanks in advance,

Kyle Jorgensen

Woozy
Veteran Member Send Private Message
Posts: 709
Veteran Member

Hi Kyle,

We do use Control-M as our enterprise scheduler, and we use it extensively for scheduling Infor/Lawson tasks.

To be honest, it's pretty clunky - but it works.  Basically, we create scripts that call Infor/Lawson utilities to do whatever we need to do - wtsubmit, rqstatus, trigger and monitor flows, etc.

Kelly

Kelly Meade
J. R. Simplot Company
Boise, ID
Kyle Jorgensen
Veteran Member Send Private Message
Posts: 122
Veteran Member

How do you trigger IPA flows with Control-M and what amount of "visibility" into the triggered process does it have?

Woozy
Veteran Member Send Private Message
Posts: 709
Veteran Member
We use a script that we developed several years ago. It uses the "dataimport" utility to update a designated PfiTrigger record with a unique WorkTitle, do another "dataimport" call to perform a "start" action on that trigger, then use a "dbdisplay" call against PfiWorkUnit grepping for the unique WorkTitle created above to monitor for completion or error. Unfortunately, there isn't a utility like "wtsubmit" that will provide a workunit number to query with.

As to visibility - there is very little. Only what you can get from a command-line query. It's also VERY VERY SLOW. It takes almost 2 minutes for the script to trigger a flow because whenever you use DataImport it has to do a buildprod. It also throws lots of warnings and errors that really don't mean anything. If the process loses a connection, or the workunit errors, someone has to log into Rich Client and review the log to see what happened.

Overall, it's pretty clunky and we have issues with long-running flows where CTM loses the connection. Currently it's all in one script, but if I was going to do it again (or had enough time to re-engineer it) I'd separate the monitor from the trigger.

I've also considered using a file channel as a trigger instead, and just let CTM drop a file - but I haven't played enough with it to make it work. And monitoring would still be an issue.

Kelly
Kelly Meade
J. R. Simplot Company
Boise, ID
Kyle Jorgensen
Veteran Member Send Private Message
Posts: 122
Veteran Member

Thanks for this information.

 

Kyle Jorgensen

WoodmenLife