PrevPrev Go to previous topic
NextNext Go to next topic
Last Post 12/16/2017 5:11 PM by  darwin collins
PO120 EDI orders
 7 Replies
Sort:
You are not authorized to post a reply.
Author Messages
bernfc10
Programmer/analyst
State
Veteran Member
(997 points)
Veteran Member
Posts:469


Send Message:

--
04/19/2016 2:44 PM
    I want to be able to run a multistep job that will create and release POs, create EDI orders and then transmit all these POS at once to GHX. Does anybody know if this is possible or do I need to schedule a PO120 and an ED501 for each vendor?

    PO100 for vendor A and location A and B, vendor B location A, Vendor C location D
    PO120 same as above
    ED501 - take all the EDI orders created by PO120 and transmit to GHX
    Kat V
    Sr Supply Chain System Analyst
    South Broward Hospital District
    Veteran Member
    (1922 points)
    Veteran Member
    Posts:656


    Send Message:

    --
    04/19/2016 5:04 PM
    Yes - We have EDIDLY (EDI Daily) that runs every 30 minutes.

    Step 1 is PO120 with the following parameters:
    Company: 1 (we only have 1)
    Draft (N)
    Selection Tab - all blank
    PO Selection - all blank
    Documents Tab: EDI Sub Tab
    Issue Y
    Form 2 (Sequential File)

    This grabs all Released, Not Issued POs set for E (EDI) and issues them.

    Step 2 is the ED501.

    Works beautifully.
    bernfc10
    Programmer/analyst
    State
    Veteran Member
    (997 points)
    Veteran Member
    Posts:469


    Send Message:

    --
    04/27/2016 8:49 AM
    Do I need a PO120 for each vendor we have setup with EDI? We have about 15 vendors
    JimY
    Private
    Private
    Veteran Member
    (1099 points)
    Veteran Member
    Posts:393


    Send Message:

    --
    04/27/2016 9:57 AM
    No you would not. In PO120 there is an EDI tab that you would enter the values needed to select PO's that are destined for EDI. In the Selection tab leave the vendor field blank.
    Kat V
    Sr Supply Chain System Analyst
    South Broward Hospital District
    Veteran Member
    (1922 points)
    Veteran Member
    Posts:656


    Send Message:

    --
    04/27/2016 3:12 PM
    No you would only need a job per Company with the vendor left blank.
    bernfc10
    Programmer/analyst
    State
    Veteran Member
    (997 points)
    Veteran Member
    Posts:469


    Send Message:

    --
    04/29/2016 1:26 PM
    OK, so I can add a PO120 for a company leave vendor blank and that will create a POEDI with all the vendors released by PO100, right?
    JonA
    Private
    Private
    Veteran Member
    (2819 points)
    Veteran Member
    Posts:991


    Send Message:

    --
    05/02/2016 7:23 AM
    As long as the POs have the PO Issue Method flag set to issue via EDI and your PO120 job is set up as Kat described above, then yes.
    Jon Athey - Supply Chain Analyst - Materials Management - MidMichigan Health
    darwin collins
    web manager
    dallas area rapid transit
    Basic Member
    (42 points)
    Basic Member
    Posts:16


    Send Message:

    --
    12/16/2017 5:11 PM
    Thanks for the info. We just went live with taking a BN106 -> EDI 834, and the boss is having us look at PO120 EDI.
    You are not authorized to post a reply.