Login
Register
Search
Home
Forums
Jobs
LawsonGuru
LawsonGuru Letter
LawsonGuru Blog
Worthwhile Reading
Infor Lawson News Feed
Store
Store FAQs
About
Forums
Financial Management
Lawson S3 Financials
AC20.4_Activity Budget by Activity
Home
Forums
Jobs
LawsonGuru
LawsonGuru Letter
LawsonGuru Blog
Worthwhile Reading
Infor Lawson News Feed
Store
Store FAQs
About
Who's On?
Membership:
Latest:
Jeffin Joy
Past 24 Hours:
0
Prev. 24 Hours:
0
Overall:
4988
People Online:
Visitors:
45
Members:
0
Total:
45
Online Now:
New Topics
Top Forum Posters
Name
Points
Greg Moeller
4184
David Williams
3349
Kat V
2984
Woozy
1973
Jimmy Chiu
1883
Kwane McNeal
1437
Ragu Raghavan
1377
Roger French
1315
mark.cook
1244
Chris Martin
825
Forums
Filtered Topics
Unanswered
Unresolved
Active Topics
Most Liked
Most Replies
Search Forums
Advanced Search
Prev
Next
Forums
Financial Management
Lawson S3 Financials
AC20.4_Activity Budget by Activity
Please
login
to post a reply.
3 Replies
0
Subscribed to this topic
45 Subscribed to this forum
Sort:
Oldest First
Most Recent First
Author
Messages
whitey1287
Basic Member
Posts: 10
7/22/2014 7:08 PM
Hi,
In AC20.4 I have a budget of $20,000 in the amount fields, but next to Total Cost Budget Amount the total is $40,000. Any guidance on this issue is greatly appreciated. Thanks!
Laura
Basic Member
Posts: 19
7/23/2014 11:08 AM
Split
Are you selecting a year in AC20.4? The Total Budget Amount shown is the LTD budget amount, but the line items will only be for the specific year you've selected. This could explain the discrepancy you're seeing.
whitey1287
Basic Member
Posts: 10
7/23/2014 11:27 AM
Split
No, I am not selecting a year because we do not use that field. There are three budget numbers. 1 (Original Budget)= $20,000...2 (Revised Budget)= $20,000. For some reason it seems to be summing these two budgets together. AC20.7 appears to be set up properly as well.
However, our final budget of $19,000 is appearing correctly in AC20.4.
whitey1287
Basic Member
Posts: 10
7/24/2014 4:22 PM
Split
I resolved the issue by running AC580; Balance Rebuild.