Login
Register
Search
Home
Forums
Jobs
LawsonGuru
LawsonGuru Letter
LawsonGuru Blog
Worthwhile Reading
Infor Lawson News Feed
Store
Store FAQs
About
Forums
Integration / Customization
IPA/ProcessFlow
LPA scheduled flows
Home
Forums
Jobs
LawsonGuru
LawsonGuru Letter
LawsonGuru Blog
Worthwhile Reading
Infor Lawson News Feed
Store
Store FAQs
About
Who's On?
Membership:
Latest:
Jeffin Joy
Past 24 Hours:
0
Prev. 24 Hours:
0
Overall:
4988
People Online:
Visitors:
128
Members:
0
Total:
128
Online Now:
New Topics
Top Forum Posters
Name
Points
Greg Moeller
4184
David Williams
3349
Kat V
2984
Woozy
1973
Jimmy Chiu
1883
Kwane McNeal
1437
Ragu Raghavan
1377
Roger French
1315
mark.cook
1244
Chris Martin
825
Forums
Filtered Topics
Unanswered
Unresolved
Active Topics
Most Liked
Most Replies
Search Forums
Advanced Search
Prev
Next
Forums
Integration / Customization
IPA/ProcessFlow
LPA scheduled flows
Please
login
to post a reply.
7 Replies
0
Subscribed to this topic
53 Subscribed to this forum
Sort:
Oldest First
Most Recent First
Author
Messages
Gary Padgett
Veteran Member
Posts: 90
1/6/2014 4:36 PM
I have set up several flows to run once daily. Some are supposed to run at night, some in early morning. It looks like the first iteration of each of these ran when it was supposed to, but all subsequent runs are running at midnight. I am sure I missed something in my schedule setup, but I don't know what. Can someone provide a little guidance? Thanks in advance.
Deleted User
New Member
Posts: 0
1/6/2014 4:53 PM
Split
If you are still on PFI (we're on 9.0.1.10) You have to defined the time in two places.
The first under the "First Run Date and Time" - and you must select the time BEFORE you select the date. The second is the "Start Time" where you pull over the desired time from the Available Hours and then adjust the minutes in the box above it.
If those check out okay you might just want to delete the schedule and create it new (there may have been corruption when it was added to the LOGAN table).
Gary Padgett
Veteran Member
Posts: 90
1/6/2014 4:57 PM
Split
No, this is LPA not PFI.
Deleted User
New Member
Posts: 0
1/6/2014 5:02 PM
Split
OK, I don't know if those still write to the LOGAN tables? If so, looking at that might provide a clue - what does the recurring_opt field on the logan.wfjobdef table look like for that job_id?
Deleted User
New Member
Posts: 0
1/6/2014 5:18 PM
Split
When you scheduled it in IPA, what frequency did you choose? If you used By Day, make sure that after clicking Next, that you choose the Hour to run it under "Year and Specific Time to Run Action". That is what controls the time of day that the flow runs.
Also, you should be able to find your scheduled task and see the next 3 run times under your My Actions in the rich client.
Erin
Advanced Member
Posts: 24
1/6/2014 5:20 PM
Split
Gary,
That happened to us. We had to set it up in military time separately from the initial run.
use Advanced Schedule Options
FYI we are on
IPA Product Version: 10.0.4.2..5772
Gary Padgett
Veteran Member
Posts: 90
1/6/2014 5:39 PM
Split
Thanks, Bob and Erin. I will make these changes and check it again tomorrow. Will report back.
Gary Padgett
Veteran Member
Posts: 90
1/7/2014 9:11 PM
Split
Yes, looks good - thanks