Scheduler

Sort:
You are not authorized to post a reply.
Author
Messages
Roger French
Veteran Member
Posts: 545
Veteran Member
    Trying to set up a new job schdedule in SCheduler...

    The ONLY process I have in the Process Name drop down list box when I try to add a new job is "Broadcast".

    However I have other processes which are NOT showing in the drop down list box..

    The process is defined in WF07.2 with the Service.

    How can I get the correct process(es) to appear in the drop down list box in scheduler?????

    Thank you,

    Roger

    PF :8.0.3.6
    Env: 8.0.3.6

    rashedchowdhury
    New Member
    Posts: 1
    New Member
      Do you have your work flow in pfrepository directory in your app server? if so, you should be able to see the process name in the drop down list box in the scheduler.

      Also, do you see the work flow you designed in wf07.2 (process definition)?
      Bill Ianni
      Veteran Member
      Posts: 111
      Veteran Member
        Also make sure you're WF12 profile has the role of PF Administrator